Bettendorf taxpayers to pay far more for sports complex streets, sewer and stormwater detention

Bettendorf taxpayers will pay far more for streets, sewers and stormwater detention than the $3.87 million stipulated in the contract with the Bettendorf sports complex developer.

In private 3-on-3 meetings with aldermen July 5, city officials outlined a summary of estimated infrastructure costs for the sports complex showing construction bids received so far are $844,000 above the cap set in the development agreement between the city and developer Douglas Kratz.

Bettendorf betting $11.2 million on sportsplex to kickstart development at I-80 and Middle Road

After secret briefings given Bettendorf aldermen in mid January, the city added $11.2 million in bonds to its proposed budget to pay for roads, sewers, stormwater detention and developer loans and rebates for a sports complex at Forest Grove and Middle Road.

According to documents and emails obtained by Bettendorf.com through a Freedom of Information request, city officials in those non-public sessions discussed with aldermen the impact the sports complex would have on next year's capital improvement plan (CIP), city tax levy and debt margin.

The project was outlined a month later at a news conference Feb. 17 by Mayor Robert Gallagher and developer Douglas Kratz, but aldermen have yet to publicly discuss the sport complex plans or its financial impact on city finances at an open city council meeting.